Mumbai-Ahmedabad high-speed rail sees ₹85,801 crore spend so far: Ministry

The rail ministry said the Mumbai-Ahmedabad high-speed rail project has achieved 55.63 per cent physical progress and 69.62 per cent financial progress as of November 30, 2025